Week commencing 10 October 

  • Unit 2 & 10 balustrade installed 

  • Unit 8 parapet wall extension completed 

  • Unit 2 & 5 internal hobs rendered 

  • Unit 2 & 3 ground floor drummy render patches cut-out and re rendered

  • Sika application to skirting tile and floor tile control joints near completion 

  • Unit 2 & 3 water blasted 

In the week ahead

  • Screed Unit 1 roof terrace 

  • Hydrepoxy Unit 1 screed 

  • Finish all Unit 7 tile works 

  • Finish Unit 5 splash back tiles

  • Complete all sika application to skirting tiles and floor tile control joints 

  • Screed and tile Unit 8 bathroom 

  • Finish all external paintings in Unit 2, 3 & 4