Week commencing 17 October 

  • Unit 1 roof screed & hydrepoxy completed 

  • Unit 7 mosaic tiles complete 

  • Unit 7 balcony and hob tiles complete 

  • Sika application to all finished tiles completed 

  • Unit 2, 3, and 4 external painting near completion

  • Unit 2 & 3 broken tiles removed 

  • Unit 8 bathroom tiling works completed

In the week ahead

  • Finish all external paintings to Unit 2, 3, 4, 5, 6, 7, and 8 

  • Finish Unit 1 roof and skirting tiles 

  • Unit 5 splash back tiles

  • Install balustrade and posts in Unit 1 

  • Install posts to balustrades on Unit 2, 3, & 8 

  • Replace all broken tiles to every unit and common area 

  • Sika Unit 1 tile junctions and control joints 

  • Install Unit 10 sprinklers 

  • Complete Unit 8 bathroom painting works 

  • Re-instate Unit 8 bathroom fittings