Week commencing 27 February

  • Wet weather delays for most of the week
  • Broke out and repaired render patches at main entry and car park entry
  • Completed painting at Aluminium Stage 6
  • Continued Megasealed works
  • Continued Sikaflex expansion joint sealant installation at LVL 2 tiling

In the week ahead

  • Complete all LVL 2 parapet wall cut-out repairs including rendering and capping
  • Finish tiling at unit 809 upper balcony including skirting and grouting
  • Install new torch-on membrane at unit 201 courtyard missing section (next to parapet wall cut-out), screed and install hydropoxy membrane
  • Commence fence installation at LVL 2 East and West courtyards, complete at Roof Top with gates installation
  • Electrician to commence new lighting installation
  • Strip and remove Aluminium Stage 6
  • Megasealed to complete all bathroom works