Week commencing 6 June

  • Balustrade removal and preparation for hob to be installed
  • Terrace plumbing to be completed
  • Inspection for scaffolds
  • Level out remaining low spots on Block A 
  • Inspection for storm-water detention tank
  • Crack repairs 
  • Block A waterproofing to be completed
  • Unit 5 & 6 staining to be completed

In the week ahead

  • Block A waterproofing to be completed 
  • Block A & B roofing to be completed 
  • Block B scaffolding to go up ( Please see note about access)
  • Terrace residents to be informed of the dates for door removal and waterproofing 
  • Terraces to have waterproofing and floor leveling completed and hobs completed