Week commencing 13 June

  • Block A waterproofing works
  • Block A & B roofing works
  • Terrace residents to be informed of the dates for door removal and waterproofing 
  • Terraces works to start 

In the week ahead

  • Block A waterproofing works and membrane depending on weather and top coat 
  • Block B timber decking to commence towards the end of the week 
  • Block B Scaffolding to go up ( Please see note about access)
  • Sliding door works 
  • Terrace works: Strip formwork, waterproofing works, leveling, hobs for services, plinth for screens, membrane works.