Week commencing 20 June

  • Block A waterproofing works and membrane depending on weather and top coat 
  • Block B timber decking to commence towards the end of the week 
  • Block B Scaffolding to go up ( Please see note about access)
  • Sliding door works 
  • Terrace works: Strip formwork, waterproofing works, leveling, hobs for services, plinth for screens, membrane works. 

In the week ahead

  • Carpentry works starting Monday for Building A 
  • Start raking out blue boards for Building B 
  • Leveling and waterproofing work for Terrace level
  • Membrane works for Terrace levels 
  • Remove second side sliding door from Unit 21, prepare hob, Waterproof and reinstall window