Week commencing 25 July

  • Waterproofing terrace Unit 21 and 30 completed
  • Unit 38, 45, and 46 glass blocks cleaned and sealed internally 
  • Unit 41 internal repairs completed 
  • Dilapidation survey and contacts collection 1/3 completed 
  • Timber decking continues in Building A
  • Continued treating the underside of decking 
  • Building B blueboard repairs (stud replacement) near completion - needs inspection 
  • Stormwater detention tank flood testing completed 

In the week ahead

  • Tiling terrace around Unit 21 and 30 to continue 
  • Balustrade re installation to start
  • Continue with dilapidation survey and contacts 
  • Timber decking to continue in Block A 
  • Continue to treat the underside of decking 
  • Complete internal works Unit 45, 46, and 41 (sills to be painted)
  • Building B blueboard to continue as per Monday inspection 
  • AC to be removed on balconies of Unit 42 and 39 and take up tiles
  • Finish defects works in Unit 21 internal 
  • Internal mould damage repair to Unit 20 
  • Start Unit 44 back balcony works on Friday