Week commencing 1 August

Stage 1 

  • Tiling terrace around Unit 21 and 30 continued
  • Timber decking in Block A continued
  • Treat underside of decking continued

Stage 2 

  • Compiling of dilapidation and contacts continued
  • AC removed on balconies 42 and 39
  • Tiles and waterproofing removed on Unit 42 back balcony
  • Started fire check plasterboard installation for hatches

In the week ahead

Stage 1 

  • Balustrade re-installation to start
  • Tiling terrace around 21 and 30 to be completed
  • Timber decking to continue in Block A
  • Internal mould damage repair to Unit 20
  • Drain install to Block A and top coat small area previously covered with protection

Stage 2

  • Complete internal works on Unit 45, 46, and 41 (sills to be painted)
  • Complete Unit 45 plasterboard repair around window
  • Remove tiles and waterproofing on Units 44, 43, and 39 (Building B top level)
  • Water test for new leak to Unit 42