Week commencing 15 August

Stage 1 

  • Timber decking Block A - 99% completed
  • Balustrade re-installation - completed
  • Tiling terrace around 21 and 30 to grouting and silicon joints - 85% completed

Stage 2

  • Compiling of dilapidation and contacts continued (waiting on Unit 37)
  • Waterproofing primer applied to Unit 39, 42, and 43 balconies
  • Unit 39 grind out rust on steel post and epoxy paint
  • Tiles taken up on balcony of Unit 29
  • Units 42 and 43 levelled out balconies to 1:100 fall
  • Unit 44 hob constructed
  • Flood test Unit 40

In the week ahead

Stage 1 

  • Privacy screens to be re-instated
  • Oxidisation at the base of privacy screen to Unit 30 to be fixed
  • Stain timber decking Block A
  • Internal mould damage repair to Unit 20

Stage 2

  • Unit 41 photographic documentation of completed works
  • Remove tiles and waterproofing from balcony of Unit 28
  • Water test for new leak to Unit 42 (tentative access for Wed)
  • Remove tiles on balconies of Unit 28 & 20