Week commencing 31 July

  • Complete pavers down the side of Unit 1.
  • Complete paver works on driveway.
  • Complete expansion joints on courtyard walls.
  • Continue with detailed cleanup of site.
  • Epoxy driveway wall and paint.
  • Fill planter box with some blue metal.
  • Put Geofabric around drain at the front planter box.
  • Complete HB40 works at entrance way stairs.
  • Complete paint works.
  • Complete all render works.
  • Continue taking materials away from site.
  • Clean site.

In the week ahead

  • Continue with final clean up of podium area and courtyards.
  • Continue with electrical works.
  • Complete painting works.
  • Put a layer of blue metal in garden area along pathway and in planter box.
  • Complete internal works.
  • Complete expansion joints.
  • Continued removal of materials from site.
  • Clean site.