Week commencing 4 April

  • Start deck on Block B timber frame and decking
  • Paint reverse side of decking
  • Carry on break out of tiles between units 21 and 30
  • Grind off waterproofing to exposed slab
  • Water test Block A slab

In the week ahead

  • Continue Block B decking
  • Inspections and floor grinding to units 21 and 30