Week commencing 7 December

  • Complete the set-up for Group 2 balconies: units 3 & 4, 9 & 10, 15 & 16 
  • And start the set-up for Group 3 balconies: units 5 & 6, 11 & 12, 17 & 18

In the week ahead

  • Complete balustrade installation. The order will be from the top unit to bottom unit within each group, starting with Group 1 through to Group 3. 

    Group 1: balconies of units 1 & 2, 7 & 8, 13 & 14
    Group 2: balconies of units 3 & 4, 9 & 10, 15 & 16
    Group 3: balconies of units 5 & 6, 11 & 12, 17 & 18