Week commencing 29 August

  • Continue with removal of toppings
  • Removal and demolition of last balcony wall and balustrade
  • Removal of rubble from balconies
  • Open areas as directed by the engineer 
  • Start installation of starter bars and form work 
  • Continue with V cuts to the balconies 

In the week ahead

  • Complete removal of toppings 
  • Removal of rubble from balconies 
  • All saved bricks to be stored together 
  • Continue with formwork and starter bar installation 
  • Expose 6 starter bar per six balconies and requested by engineer 
  • Start concrete pour for newly formed hobs