Week commencing 5 September 

  • Complete removal of toppings 
  • Removal of rubble from balconies 
  • All saved bricks to be stored together 
  • Continue with formwork and starter bar installation 
  • Expose 6 starter bar per six balconies and requested by engineer 
  • Start concrete pour for newly formed hobs 

In the week ahead

  • Continue with steel repair to 6 central balconies
  • Strip formwork off poured hobs 
  • Render newly poured hobs 
  • Continue to form new hobs and installation of reinforcement starter bars
  • Repair balcony tops to 6 central balconies 
  • Grind paintwork on soffits 
  • Spalling repair to any exposed steel