Week commencing 19 September 

  • Continued with steel repairs to balconies 
  • Rendered hobs on balconies 64, 67, and 70
  • Repaired balcony tops to central balconies 
  • Continued grinding paint off soffits
  • Continued with spalling repairs 
  • Checked measure of newly rendered hob
  • Repaired to face of balconies where required
  • Installed spitters to balconies 64, 67, and 70 

In the week ahead

  • Continue with steel repairs to balconies 
  • Repair balcony tops to six central balconies 
  • Continue grinding paint off the soffits
  • Form up six central balcony hobs after approval 
  • Installation of starter bars 
  • For balconies with hobs completed start finding levels for toppings