Week commencing 4 October  

  • Steel repairs to balcony for balcony 60 
  • Repair top to balcony 60 slab 
  • Continued grinding paint off soffits 
  • Continued with spalling repairs 
  • Installation of starter bars and formed up new hobs on five of the six central balconies 
  • Levels for toppings on balconies 
  • Brickwork cleaned where old brick wall tied to unit

In the week ahead

  • Continue with installation of starter bars and form work 
  • Continue with spalling repairs 
  • Fill all spalling repairs with HB 40 
  • Installation of L bar reinforcement for slab face and hob ready to pour in one go 
  • Continue cleaning brickwork 
  • Continue finding levels for topping on balconies 
  • Complete grinding off paint from soffits
  • Start rendering soffits 
  • Complete repairs to balcony 60 slab