Week commencing 17 October  

  • Formed up and pour three remaining hobs in the central six balconies 
  • Started rendering soffits of the six central balconies 
  • Rendered the three hobs that were poured on the earlier Friday 
  • Started finding the levels for balcony toppings 
  • Started installation of the drip angle to soffits 
  • Started painting soffits
  • Cleaning in the scaffolds
  • Started cleaning bricks with brick acid and jet wash 
  • Cleaning saved bricks from any mortar 

In the week ahead

  • Render remaining soffits and hobs 
  • Install drip angle 
  • Paint soffits 
  • Complete check measures on remaining hob 
  • Finish cleaning saved bricks 
  • Clean brickwork on balconies 
  • Finish installing spitter pipes
  • Start installing toppings