Week commencing 31 October  

  • Complete topping levels

  • Start installation of toppings

  • Install drip angle

  • Clean site 

In the week ahead

  • Continue with installation of toppings
  • Install construction joint to toppings that are completed
  • Install bond breaker on balconies for waterproofing
  • Continue with installation of drip angles
  • Start putting down Westox WB30
  • Start installation of Westox Wesdex membrane 
  • Cut spitter pipes to correct measurments
  • Clean site