Week commencing 07 November

  • Continue installation of toppings

  • Install construction joint to toppings that are completed

  • Install bond breaker on balconies for waterproofing

  • Continue installation of drip angles

  • Start putting Westox WB30 down

  • Start putting Westox Westdex liquid membrane down

  • Cut spitter pipes to correct measurements 

In the week ahead

  • Complete installation of toppings
  • Complete installation of drip angles
  • Complete installation of expansion joints/bond breakers
  • Complete installation of Westox WB30
  • Complete installation of Westox Westdex liquid membrane
  • Start painting soffits
  • Clean site