Week commencing 14 November  

  • Complete installation of toppings
  • Complete installation of drip angles
  • Complete installation of expansion joints/bond breakers
  • Complete installation of Westox WB30
  • Complete installation of Westox Westdex liquid membrane
  • Start painting soffits
  • Clean site

In the week ahead

  • Complete drip angle installation
  • Complete bond breaker installation
  • Continue with installation of Westox Westdex
  • Continue with installation of Westox WBA9000
  • Continue with balustrade installation
  • Clean site