Week commencing 12 December

  • Continue 'peel away' paint removal of southern elevation
  • Survey for render works
  • Start approved render & spalling repair worksto western and southern elevation to 3m
  • Continue preparation to roof top and pool area substrate and parapet walls

In the week ahead

  • Continue preparation for rooftop terrace and pool works
  • Continue render survey
  • Commence render repairs
  • Trial Ardex System to external facade
  • Remove Christmas