Week commencing 09 January

  • Organise scaffolding and hoarding
  • Continue basement & ground floor paint removal
  • Continue basement & ground floor render repairs 

In the week ahead

  • Complete basement & ground floor paint removal.
  • Continue basement & ground floor render repairs 
  • Commence colorbond roof corrosion repairs
  • Acquired approval for erection of scaffold to Little Campbell St.
  • Acquired approval for erection of hoarding to Crown St and Campbell St.