Week commencing 16 January

  • Complete basement & ground floor paint removal.
  • Continue basement & ground floor render repairs 
  • Commence colourbond roof corrosion repairs.
  • Acquired approval for erection of scaffold to Little Campbell St.
  • Acquired approval for erection of hoarding to Crown St and Campbell St.

In the week ahead

  • Access to units ear marked for water testing and waterproofing.
  • Commence tile breakout to the above.
  • Preparation work for the arrival of the hoarding.
  • Survey to eastern facade and continue render & spalling repairs.