Week commencing 23 January

  • Access to units ear marked for water testing and waterproofing.
  • Commence tile breakout to the above.
  • Preparation work for the arrival of the hoarding.
  • Survey to eastern facade and continue render & spalling repairs

In the week ahead

  • Install of hoarding to Crown st and Campbell st
  • Continue render survey and repair
  • Continue tile breakout to nominated balconies
  • Continue replacement of corroded roof fixings
  • Water testing of remaining balconies as specified