Week commencing 30 January

  • Install of hoarding to Crown st and Campbell st
  • Continue render survey and repair
  • Continue tile breakout to nominated balconies
  • Continue replacement of corroded roof fixings
  • Water testing of remaining balconies as specified

In the week ahead

  • Completion of Class B hoardings
  • Erection of Steel scaffold 
  • Preparation work for lead paint removal, Crown St
  • Additional hoarding as required to Shop entrances
  • Continue of render survey and repair