Week commencing 06 March

  • Prepare for remaining balcony works (Crown St and North elevation)
  • Level 2 to rooftop prepared and primed for first coat of membrane
  • Completion of lead paint removal to Crown St
  • Tap test and survey to Crown St elevation
  • Commence window flashing to Level 2 

In the week ahead

  • Continue survey and render repairs to North elevation
  • All prep work to specified balconies completed and made ready for waterproofing
  • Commence Crown St window works