Week Commencing 17 April

  • Install new led flashing.
  • Break out and brick up of facades and brick piers.
  • Waterproofing internal cavities.
  • Unit 7 spooling works.

In the weeks ahead

  • Unit 6 and 7 balcony brick work and flashing's.
  • Unit 7 bathroom plastered.
  • Unit 7 sun-room inspection from triaxial.
  • Unit 7 HB40 repair (sun-room).
  • Render work to underside of slab and slab edges.
  • Unit 4 render works in bedroom.
  • Brick work acid wash.
  • Unit 4 break out in dining room (more spooling evident) plus mark up from engineer.
  • Unit 7 tile breakout.