Week commencing 06 February

  • Complete asbestos removal
  • Complete courtyard deck waterproofing
  • Start entrance floor tile removal
  • Start balustrade removal
  • Start dividing wall Unit 8 removal
  • Disconnect Unit 2 A/C
  • Start V cut courtyard skylight and fill with sealant

In the week ahead

  • Balustrade removal
  • AC unit disconnected
  • Remove unit 1 pavers and store in allocated area
  • Drop unit 1 dividing wall (possible)
  • Continue grinding water proofing to common area and units
  • Continue with spalling repair
  • Install hobs (possible)
  • Repair and patch spalling
  • Clean site