Week commencing 13 March

  • Continue preparation/construction for new balustrade hobs, dividing walls and south side stairs
  • Preparation works for water proofing membrane – complete render band
  • Remove podium lights
  • Continue garage spalling repairs
  • Dig out and change square down pipes to round

In the week ahead

  • Complete infill of cavity and hob detail 
  • Start installation of starter bars for dividing walls 
  • Start formwork for dividing walls 
  • Start formwork for stairs at south side
  • Complete render band on cavity brick for water proofing 
  • Dig out around pipes to change fitting from square to round 
  • Remove podium lights 
  • Continue with spalling works
  • Progressive cleaning up of site