Week commencing 06 March

  • Complete removal of bricks for waterproofing and cavity flashing
  • Start infill of cavity with a 45 angle of concrete for waterproofing
  • Complete form work for balustrade hob and pour (weather dependant)
  • Drill hole in slab for electric cable
  • Start starter bar's for dividing wall hobs
  • Complete floor grinding of common areas and units

In the week ahead

  • Continue preparation/construction for new balustrade hobs, dividing walls and south side stairs
  • Preparation works for water proofing membrane – complete render band
  • Remove podium lights
  • Continue garage spalling repairs
  • Dig out and change square down pipes to round
  • Maintain site cleanliness