Week commencing 20 March

  • Complete form work for cavity detail
  • Complete infill of cavity detail
  • Commence concrete pour for dividing wall plinths
  • Remove podium lights
  • Start waterproofing cavity's
  • Start waterproofing plinths for dividing walls
  • Start formwork for landing and stairs to garage area
  • Continue with spalling repair
  • Start installation of electrical works for lighting to dividing walls
  • Start removal of brick work at entrance way – 6 courses

In the week ahead

  • Continue with cavity waterproofing detail
  • Start waterproofing hobs for dividing walls
  • Start cavity flashing and brick work to cavities
  • Start removal of brick wall at entrance way – 6 courses down
  • Remove pavers and tiles at entrance way
  • Continue with spalling repair
  • Start core drilling for new down pipes and drainage